Cooling Ramp & Gear Towers

Time: 8 Hours

Today started with a few work related tasks and a couple of errands. When I got home I got right to the Hangar for some more work. First task to rivet the cooling ramp stiffener in place and the cooling ramp attach bracket to the forward floor substructure. The stiffener was done with the back rivet set and I was able to get the others with the pneumatic squeezer.

IMG_3651.JPG

IMG_3652.JPG

IMG_3653.JPG

IMG_3650.JPGAfter that I moved on to the gear towers. All the parts need to have all the edges deburred as well as all the lightening holes. That took several hours to get accomplished. Now on to one of the “mods” I will be doing to my RV-8. When the gear tower is completed it is a pretty tight space on the inside. The main gear attach bolts will be housed inside of the tower at its bottom going through the floor to the steel gear legs. You have to check and torque these at a regular interval. Van’s only gives you a stretched circular hole in which to access the nuts for torquing. It’s well known in the RV circles that this is a pain in the butt to say the least. So down the road someone came up with a modification idea that would help this task. Basically it’s a access plate that opens this area up for access. There have been several different styles or mods that various builders have used. I decided to go with what was proven, my buddy Glens style, and did a rectangular panel. This will allow me to use the angle structure for the support and will just replace the stock rivets with #8 nutplates to screw the plate to.

IMG_3654.JPGSo I took several measurements ant came up with a good panel size. The top will be at a slight angle as the rivets are not matched between the forward and aft sides. This will allow me to have the screw holes in a straight line although at an angle. Once I had the idea on paper I transferred the lines to the panels.

IMG_3655.JPGI then made the cuts on the band saw going very slow to make nice straight cuts. My blade made about a 1/16″ gap between each panel but that will be backed by a filler piece behind which will have a couple nutplates in it.

IMG_3656.JPG

IMG_3657.JPGOnce I had the access plates cut and cleaned up I needed to fabricate 4 pieces of aluminum to act as backers to the top and bottom of the plate.

IMG_3660.JPG

IMG_3658.JPGWith the plate backers done and fitting just right I moved on to the top and bottom pieces of the panel. I needed to mark out 4 rivets on the ends that match up with the access plate. These will be flush rivets and hold the plate backers in place.

IMG_3659.JPGI enlarged all the perimeter holes to a #19 that will accept the #8 screws. All of the perimeter holes will need nutplates for the screws to go into. That’s where my new tool, the nutplate jig, came in to play.

IMG_3661.JPG

IMG_3662.JPG

IMG_3663.JPGI was able to get the 16 nutplates drilled in 10 minutes, man I love this tool! I put all the parts back together and cleaned up the Hangar. That’s 8 solid hours of build time and it was a great day!

IMG_3665.JPG

IMG_3664.JPG

Firewall Done, Forward Floor Work

Time: 7 Hours

After my regular weekend breakfast with the guys I headed home to get to work in the Hangar. First up was to finish the riveting of the substructure to the firewall. There were 3 rivets in each of the lower engine mounts that I could not get with the back rivet set. I thought long and hard about how to tackle these rivets by myself. Trying to hold the metal, bucking bar and the gun at the same time proved to be a problem. An idea popped in my head, why can’t I use the DRDT to dimple these rivets. If I’m carful I could get these done with out damaging the machine. I had to take a couple of parts off of it so that I could get a straight shot at the rivets. In the end it worked like a charm. With all the firewall rivets done I moved to the nulplates on the firewall with the back rivet set. Next would be the rivets on the flanges of the substructure that would eventually hold the baggage compartment floor in place. The plans tell you to do this step before doing all the other riveting on the firewall. The problem is that with these nutplates riveted in place cause a problem for several of the firewall rivets and the back rivet set. The way I did it was simple and had no issues.

IMG_3627.JPG

IMG_3628.JPG

IMG_3629.JPG

IMG_3630.JPG

IMG_3631.JPG

IMG_3632.JPG

IMG_3633.JPG

IMG_3634.JPG

IMG_3635.JPG

IMG_3636.JPG

IMG_3637.JPGWith all the firewall rivets done I moved on to the forward floor section. This was pretty simple to do with the back rivet set. I just took my time looking at the plans as there are certain areas that don’t get riveted now. I started with the nutplates on the cross members and then moved to the floor.

IMG_3638.JPG

IMG_3639.JPG

IMG_3640.JPG

IMG_3641.JPGThat’s as far as you go for now on the forward floor. The next task was to work on the cooling ramp. I’m not totally sure what this ramp does for cooling just yet. It gets riveted to the lower part of the firewall in the front and curls under going aft and tapers as it goes towards the back. I’m sure I will understand as I get farther down the build. I just needed to trim each side of the ramp to a prescribed angle, deburr the edges, deburr the holes, dimple the holes and prime.

IMG_3642.JPG

IMG_3643.JPG

IMG_3644.JPG

IMG_3645.JPGWhile the primer was drying between coats I started the next task which it the gear towers. These towers will tie the main landing gear to the fuselage and is what gives the RV-8 it’s incredible gear strength. I started by fluting the flanges if the forward and aft walls of the towers on both the left and right gear towers. This will allow them to sit flat.

IMG_3646.JPG

IMG_3647.JPGI separated and deburred the heavy angle aluminum pieces that tie the gear towers to the forward floor. With those done I clecko’d all the parts together.

IMG_3648.JPGI decided that 7 hours was enough and felt like this has been a great weekend in the Hangar. My flight schedule is light this week, so I should get in some good Hangar time over the next few days.

Firewall Riveting

Time: 4 Hours

I got started in the Hangar around 9 this morning. The weather is perfect out, a few clouds in the sky and mid-70’s. I grabbed all the firewall parts off the paint rack and checko’ed them to the firewall while trying to be careful so I didn’t scratch the paint. I’m guessing it will take several weeks for it to cure fully. Most of the rivets I will be able to get with my back rivet set.

IMG_3609.JPG

IMG_3606.JPGThe riveting went well, only had to drill out a couple when the head slipped off the back rivet plate since there isn’t a lot if room between the firewall flanges.

IMG_3608.JPG

IMG_3607.JPGI got most of the rivets done by lunch time and had offered my help to my buddy Glen to rivet the top skin on his RV-8 tail cone. I was really nervous running the rivet gun on his plane but everything turned out perfect.

IMG_3614-0.JPGYou can see how tight it is in there to buck!

IMG_3613.JPGDecided to have dinner and sit by the fire pit at his house tonight so I will get back at the firewall tomorrow.

Forward Section Work

Time: 5 Hours

I decided to let the paint cure for a day on the firewall parts. With those parts waiting to be riveted it decided to move ahead and get some of the forward floor section work done. All the substructure got match drilled and deburred. There are several different areas on the floor that get flush rivets and others that don’t. There will also be areas that get riveted now to just the floor and substructure. Other areas will get riveted later with parts of the firewall and gear towers. I studied the plans for a good time making sure I knew just how the layout goes. I marked and dimpled the holes in the floor, making sure to only do the ones that the plans call for. I also marked all the #40 holes for the nutplates that needed to be machine countersunk for flush rivets by marking a CS next to them.

IMG_3600.JPG

IMG_3601.JPG

IMG_3603.JPG

IMG_3604.JPGAfter the floor was dimpled I marked all the corresponding holes in the 2 cross members so that I could countersink them to match the dimples.

IMG_3602.JPGI then grabbed the pneumatic squeezer and dimpled all the required holes in the 4 floor ribs.

IMG_3605.JPGIt takes me a while to visualize the layout if the floor as they show it upside down in the plans since the substructure goes on the underside of the floor. I have to always recheck my work before I actually do it so that I don’t make any mistakes, which takes time! One option for the RV-8 is to have inflight adjustable rudder pedals or ground only adjustable ones. I chose the ground only for a couple of reasons, I didn’t like the looks of the inflight ones and I’m gonna be the only one flying it and won’t have to adjust them very often. As I was looking at the floor section planning my next move I noticed that there were not any rivet holes for the brackets that hold the rudder pedals in place. That got me to do some digging in the plans for how they will be installed. It turns out that the inflight adjustable ones are the standard and the ground ones are a build change. Not a big deal but as I was looking ahead in their plans I found that you would have to drill out a few rivets in different spots to go from universal rivets to flush ones to accommodate the new brackets for the pedals. So with a little planning now on parts that I will be working with on the firewall and gear towers I will save myself some work. Mainly I will just countersink the parts for flush rivets and not rivet those spots until I install the pedals. I makes the parts so that I will remember later.

IMG_3599.JPGI now have all the forward floor parts done and ready for priming. I will let the primer dry overnight and will be able to rivet them as well as the firewall structure, if the paint feels cured enough for me.

Firewall Painting

Time: 2 Hours

I have been pretty busy flying at work this week and haven’t had the time to get much work done in the Hangar. When I got home tonight I decided that I need to get something done even if it’s just a little. The primer on all the firewall support pieces was dry so I grabbed my final color spray paint. I decided to go with a granite gray that is a satin finish similar to the cockpit of the Lear 45. I found this color in a Rust-Oleum rattle can which will make it pretty easy to paint. I’m hoping that I can get good results that are constant. Only time will tell!

IMG_3593.JPG

IMG_3592.JPG

IMG_3594.JPGI decided to move ahead in the plans as I wait for the paint to dry. The next step it to work on the forward floor assembly. 12 nutplates have flush rivets holding them in place on the floor substructure, so I machine countersunk them.

IMG_3596.JPGThen I checko’ed all the parts together for match drilling.

IMG_3595.JPGI also bought a $14 portable clothes rack on Amazon to use as a paint dryer for hanging parts.

IMG_3597.JPGMy second parts bin also arrive from Amazon today.

IMG_3598.JPGI have a 3 day weekend starting tomorrow so I’m hoping to get some good work done on the RV as well as some organization in the Hangar. I will also probably help my buddy rivet the top skin of the tail cone on his RV-8 this weekend. Short time in the Hangar tonight but good progress.